The lower level of Blakely Hall will be affected by this renovation work, renovating 4,880 gsf. Spaces to be provided include: two classrooms, seminar room with video technology, curriculum room, gender neutral restrooms, custodial room, and new spaces created in transitional spaces: collaboration space/individual work areas. A major challenge of this renovation is creating new HVAC systems while maintaining existing systems for the second level and third level (to be renovated at a later date).
Project | Blakely Hall instructional Classroom Improvements |
---|---|
Design | Engan |
Construction | Terra |
Gross Square Footage | 4,880 |
Project Cost | $2,400,000 |
Construction Start | July 2019 |
Completion | January 2020 |