Twin Cities Campus | East Bank
This project will consolidate and relocate undergraduate General, Life Sciences, and Organic Chemistry courses currently housed in Smith Hall and Kolthoff Hall to a transformed Fraser Hall.
New labs will support the modern methods of process-oriented, active learning for the
undergraduate student. Consolidating the space needs for these courses allows Fraser Hall to emerge as a hub and community for undergraduate students of all disciplines.
The project is utilizing the State of Minnesota B3 guidelines (which includes SB2030 Energy Standard) to meet sustainability goals for site, water, energy, indoor environment, materials and waste.
Click here for current updates
Project | Fraser Hall - Chemistry Undergraduate Teaching Facility |
---|---|
Design | BWBR / VJAA |
Construction | Mortenson |
Gross Square Footage | 117,435 gsf |
Project Cost | $ 131,614,000 |
Construction Start | June 2023 |
Completion | July 2025 |