Humanities Building Instructional Classroom Improvements
Morris Campus
All three levels of the Humanities Building will be affected by this renovation work for a total of 16,800 gsf, including five classrooms, language teaching center, media screening room, two seminar/conference rooms, seminar/presentation lounge, and transitional/collaborative space. The shell of the original spaces will remain while finishes, furniture, and technology create more functional collaborative spaces that enhance today’s educational experience.
Project | Humanities Building Instructional Classroom Improvements |
---|---|
Design | Engan |
Construction | Terra |
Gross Square Footage | 16,800 |
Project Cost | $2,400,000 |
Construction Start | May 2019 |
Completion | August 2019 |