PWB 4th Floor Teaching Lab Renovation
Renovation of the 4th Floor of PWB for new Teaching Classrooms to serve the BME and IBP Departments. Classrooms were relocated from Moos Tower and will serve as a more of an active learning style configuration.
Project | PWB 4th Floor Teaching Lab Renovation |
---|---|
Design | Perkins&Will |
Construction | JE Dunn |
Gross Square Footage | 20,100 |
Project Cost | $10,600,000 |
Construction Start | December 2021 |
Completion | December 2022 |