Field House Exterior Envelope
Field House Exterior Envelope

Twin Cities Campus | East Bank

The Field House Exterior Envelope and Flooring project revitalizes the Field House and extends the useful life of the building. Existing Cemesto (asbestos) exterior panels were abated and replaced with a new exterior insulated metal panel and translucent glazing system. Existing mechanical and ventilation system was enhanced and code upgrades completed to support a capacity of 1,500 occupants. This project also adds 80,000 sf of new track and turf flooring suitable for both Recreation programs and NCAA level competition indoor track and field events.

Project Field House Exterior Envelope
Design Cunningham Group
Construction Mortenson
Gross Square Footage 180,000
Project Cost $7,4000,000
Construction Start March 2019
Completion October 019