Lab School‐Child Development Center Unified Building Project (Child Development Laboratory School CDLS),
Twin Cities Campus
The project renovates the existing facility of 18,700 SF and provides a new 12,000 SF addition tocombine the relocated Lab School and the Child Development Center into a unified program.
| Project | Lab School‐Child Development Center Unified Building Project (Child Development Laboratory School CDLS), |
|---|---|
| Design | Miller Dunwiddie |
| Construction | Terra Construction |
| Gross Square Footage | 30,700 |
| Project Cost | $11,000,000.00 |
| Construction Start | June 2020 |
| Completion | August 2021 |